A Ripley contractor turned in the apparent low bid Tuesday for US 72 repair in Tishomingo County. WG Construction Company bid $12,525,154.54 for the work east of Iuka, about $2.5 million below the state’s own estimate, according to bid results posted by the Mississippi Department of Transportation.

The contract covers concrete repair, sealing and overlay on about 5.9 miles of US 72, from the west end of State Route 25 to the Alabama state line. It also includes repairs to the two US 72 bridges over Highway 25.

US 72 repair bids in Tishomingo County

Four companies bid on the job. MDOT’s “as read” results list them in this order:

  • WG Construction Company, Inc., Ripley: $12,525,154.54
  • APAC-Mississippi, Inc., Richland: $12,643,613.74
  • Falcon Contracting Company, Inc., Columbus: $13,470,619.31
  • Cook & Son, LLC, Smithville: $13,584,722.18
  • State estimate: $15,059,821.26

The two lowest bids were close, separated by $118,459.20, or less than 1%. All four came in under the state estimate, and the low bid was about 17% below it. MDOT had earlier placed the combined project in a range of $15 million to $20 million.

What happens next

The posted results are marked as an unofficial document, and a low bid is not a contract award. MDOT has published “checked” results and a separate list of awards after past lettings, so the figures could be updated.

The letting documents we reviewed do not give a construction start date, and they do not describe lane closures or detours. Work would begin only after a contract is awarded and MDOT tells the contractor to proceed.

What the project includes

MDOT’s notice to contractors, issued ahead of Tuesday’s bid opening, gave the project 189 working days. It listed these advance quantities, which the department describes as information only and subject to change:

  • More than 47,000 tons of asphalt pavement.
  • About 5,336 square yards of concrete pavement removal.
  • Hydrodemolition of 2,668 square yards of bridge deck, plus new bridge deck overlay concrete.
  • 24 bearing replacements, joint repair and new joint seals on the bridges.
  • 21 miles of ground-in rumble strips, along with new striping and reflective markers.

US 72 is the main east-west route through Corinth, Burnsville and Iuka, and the section in this contract carries traffic to and from northwest Alabama.

Other work in the November letting

Tishomingo County’s project was the only one in Alcorn, Prentiss or Tishomingo counties on Tuesday’s bid sheet. Elsewhere in Northeast Mississippi, Phillips Contracting of Columbus was the apparent low bidder at $561,900 to build a bulk salt storage building in Lee County.

Source: Mississippi Department of Transportation, As Read Bid Results, Nov. 24, 2026

Project details: MDOT Notice to Contractors

Related: MDOT Seeks Bids on $15M-$20M US 72 Repair Near Iuka | MDOT Lane Closures Pause for Thanksgiving in Corinth Area

Jon R Myers

Jon R Myers is the executive editor of Alcorn County News and the founder of the Mississippi News Group, which he started in 2013 to cover communities across North Mississippi. He also founded the Mississippi Sports Group in 2006, which grew from a single community publication into a statewide network covering high school and college athletics. He reports on local government, public safety, schools and community life in Corinth and Alcorn County, working from public meetings, agency records and interviews with the people involved. Contact him at editor@alcornnewsms.com with news tips or corrections. For a correction, include the article link and supporting source material.

Stay connected

Your community. Wherever you are.

Follow Alcorn County News on Facebook for local news from Corinth and across Alcorn County.

Follow on Facebook